agenthropic — Consolidated Analysis & Implementation Plan

⚠️ SUPERSEDED (2026-07-04; banner added 2026-07-06). Part A’s decisions D1–D7 were re-resolved as LB1/LB2 + CD-1…CD-10 in concept-analysis-v2.md; Part B’s phased plan was replaced by the 75-WP development-plan.md as amended by best-path-decision.md §6. Its phase numbering is the OLD scheme (see finding PROC-6). Keep for the audit trail; do not act on it. Current entry point: PROJECT-STATE-2026-07-06.md.

Companion to concept-analysis.md. Part A re-runs the four-lens review in decision form — every open question resolved into a recommendation with a rationale. Part B turns those decisions into a sequenced, testable, coverage-gated build plan that honours the project’s non-negotiable security invariants (docs/ai/DESIGN.md §8) and Ivan’s delivery bar (>90% coverage · README badges + donation · GitHub Pages docs site).

Status (as written, 2026-07-04): plan only — no code scaffolded. The stack/structure decisions below are recommendations to approve, consistent with DESIGN §10 leaning.

Status correction (2026-08-15): the code has since been scaffolded and built, and the delivery bar quoted above shipped at 100% coverage rather than >90%. This document is still superseded and still must not be acted on; the correction is here only so that a reader who arrives at this page first does not carry away a picture of the repository that stopped being true on 2026-07-11.


Part A — Re-run analysis, as decisions

The concept review surfaced seven open questions. Here each is resolved. These resolutions are the plan’s premises; changing one changes the plan.

D1 — Ingest primacy: JSONL-primary, hooks-for-liveness

Decision. Treat ~/.claude/projects/*.jsonl as the primary, durable source of truth; tail-follow it and replay-on-startup. Use hooks only for sub-second liveness (instant “agent started/stopped” signals) and for events JSONL doesn’t carry. Every write is an idempotent upsert keyed on a stable event id, so hooks and JSONL converging on the same fact never double-count. Why. It makes history crash-tolerant and backfillable (the dashboard can be down and lose nothing), it satisfies the “tokens never inferred” invariant naturally (tokens come from the ground-truth log), and claude-code-templates already proves the chokidar-watch-over-JSONL pattern works. Hard dependency: Phase-0 must confirm JSONL actually carries the subagent parent→child linkage. If it does not, fall back to hooks-primary + a local outbox/spool for at-least-once delivery — but only then.

D2 — Identity: personal-first, commercial-clean

Decision. Build the single-user Mac Mini tool. Adopt only the cheap commercial hedges now — MIT-clean code only, instance/host key on rows, a schema that wouldn’t block tenancy later — and explicitly defer every expensive commercial feature (fleet aggregation, multi-tenant isolation). Why. Resolves the identity split (concept §5.2) without paying for a product nobody is using yet; keeps the door open at near-zero cost.

D3 — v1 daily-questions (the MVP definition of value)

Decision. v1 must let Ivan answer, from real sessions:

  1. What is the subagent tree of this session, and which branch is still running?
  2. Which agent/subagent burned the most tokens (and roughly what did it cost)?
  3. Did any session get stuck / error without me noticing?
  4. What did today/this week cost, and how much did Haiku/Sonnet routing save?
  5. Show me last night’s sessions — persisted, after a restart. Why. Scope is driven by these five questions, not by feature-parity envy. Q1–Q3 define Phase 1; Q4 is Phase 4’s tile; Q5 is the persistence guarantee threaded throughout. Anything not serving a question waits.

D4 — Stack: approve the lean, with two refinements

D5 — Phase 3 (vector-DB context feed): move to an experimental track

Decision. Remove “observability becomes memory” from the core delivery line; label it future/experimental. It must not compete with shipping the cockpit. Why. It’s a different product with a large undefined dependency (concept §5.3).

D6 — Pricing source-of-truth: one dated constant, under test

Decision. A single model_pricing seed (dated, with model IDs) is the source of truth; a test asserts every model seen in fixtures has a price, and the constant carries a “verified on " stamp. Re-verify rates on each cost-feature change. **Why.** Turns a silent staleness liability (concept §6.4) into a failing test.

D7 — Secret home: environment + tight file perms, never in the app’s data path

Decision. Telegram bot token via a launchd-injected env var (or a chmod 600 dotfile the service reads at boot); never stored in SQLite, never sent to the browser. ANTHROPIC_API_KEY stays out of the dashboard env entirely (only the experimental/Phase-3 track would need it, and it’s deferred).

Cross-cutting policy resolved here


Part B — Implementation plan

B.0 Guiding principles

  1. Resolve the make-or-break unknown first. Phase 0 exists to answer R1 (can JSONL rebuild the tree?) before any architecture is poured.
  2. Every phase is independently shippable and independently useful to Ivan.
  3. The security invariants and the >90% coverage gate are load-bearing from Phase 1 — not a hardening pass at the end.
  4. Test infrastructure (fixtures + reconciliation + security tests) is a first-class, phase-spanning workstream, not overhead.
  5. Copy only MIT-clean code; reimplement everything else clean-room.

B.1 Cross-cutting workstreams (run through every phase)


Phase 0 — Validation spike (GO/NO-GO gate) 🔴 do this first

Objective: de-risk the concept’s two make-or-break unknowns before committing architecture. Throwaway code is fine.

Tasks

Gate G0 (decision):

Definition of Done: a one-page spike report (append to WORKLOG.md) recording the ingest decision, the verified hook catalog, and the tree/tokens confirmation. No production code.


Phase 1 — Hardened internal cockpit (the MVP)

Answers daily-questions Q1–Q3, Q5. This is the first thing Ivan uses daily.

Scope

Cross-cutting (must land in this phase, not later):

Acceptance criteria (Definition of Done)


Phase 2 — Telegram integration

Answers Q3 remotely (“did anything get stuck/error while I was away?”).

Scope

Acceptance criteria


Phase 3 — Delegation-savings tile (cost moat)

Answers Q4. (Re-sequenced ahead of the old vector-DB Phase 3 per D5.)

Scope

Acceptance criteria


Phase 4 — Global persistent per-instance DAG (the deep moat)

The differentiator no rival delivers.

Scope

Acceptance criteria


Phase 5+ — Deferred (explicitly out of the near-term line)


B.2 Definition of Done — global (applies to every shippable phase)

  1. All phase acceptance criteria met.
  2. >90% coverage, CI-gated and green (blocking merges).
  3. Security-invariant tests green (loopback, token, SSE origin, no-spawner, no-SSRF).
  4. README badges all green/true (via badges skill) + donation section present.
  5. GitHub Pages docs site builds and publishes the phase’s user-facing docs.
  6. WORKLOG.md entry appended (per the worklog skill).
  7. No all-rights-reserved code copied; grafts attributed (MIT sources only).
  8. Loopback-only invariant intact; the public docs site does not expose the app.

B.3 Sequencing rationale (one line each)

B.4 Risk → mitigation → phase (traceability to the concept review’s register)

| Risk (concept §9.10) | Mitigated by | Phase | |—|—|—| | R1 JSONL can’t rebuild tree | G0 spike; JSONL-primary or outbox fallback | P0 | | R2 Token double-count on replay | Idempotent upsert + replay test | P1 | | R3 All-rights-reserved code copied | Clean-room rule; MIT-only copy | P0 policy / all | | R4 Stale pricing | Dated constant + coverage test | P3 | | R5 Scope diffusion | Daily-questions MVP; Phase-3 deferred | P0 / all | | R6 Missed SubagentStop | Watchdog + unknown state | P1 | | R7 Unbounded DB / full payloads | Retention + redaction policy | P1 | | R8 Security drift | Invariant tests + grep gate in CI | P1 | | R9 Hook-catalog assumptions | G0 verification | P0 | | R10 Coverage theatre | CI gate blocking <90% | P1 |

B.5 Immediate next actions (to start Phase 0)

  1. Approve the Part A decisions (D1–D7 + licensing/security policy) — or amend.
  2. Run G0.1–G0.4 on the Mac Mini; write the spike report into WORKLOG.md.
  3. On a ✅ gate: scaffold the pnpm monorepo skeleton (server / web / shared / hooks) with the CI coverage gate and security-invariant test harness wired in from commit one — never retrofitted.
  4. Update docs/ai/DESIGN.md so the design of record reflects the resolved decisions (SSE, JSONL-primary, clean-room licensing rule) and Ivan’s delivery bar (coverage/badges/donation/Pages).

Plan is a living document — revise as Phase 0 findings and real usage refine the sequencing. No code until the Part A decisions are approved and Gate G0 is green.